home > Construction Progress > Star Wars > 02.08.19
02.08.19 - An overview from the Mickey and Friends parking structure
An overview from the Mickey and Friends parking structure 02.08.19
02.08.19 - Starting on the left side the background spires look complete now and the scaffolding is removed.
Starting on the left side the background spires look complete now and the scaffolding is removed. 02.08.19
02.08.19 - Cranes up near the center of the village as we pan to the right, but no signs of what they are working on.
Cranes up near the center of the village as we pan to the right, but no signs of what they are working on. 02.08.19
02.08.19 - Scaffolding still up on the back side of these formations.
Scaffolding still up on the back side of these formations. 02.08.19
02.08.19 - The back of this formations is taking shape with concrete being applied.
The back of this formations is taking shape with concrete being applied. 02.08.19
02.08.19 - A closer look at the background spires.
A closer look at the background spires. 02.08.19
02.08.19 -
02.08.19
02.08.19 - You can guess where the sight lines from most of the park end by where the detail and color stop.
You can guess where the sight lines from most of the park end by where the detail and color stop. 02.08.19
02.08.19 - This formation looks to be nearing completion.
This formation looks to be nearing completion. 02.08.19
02.08.19 - Wire mesh is being added to the back of this formation as they close up these formations.
Wire mesh is being added to the back of this formation as they close up these formations. 02.08.19
02.08.19 - Scaffolding still up in this area.
Scaffolding still up in this area. 02.08.19
02.08.19 - Concrete has been added to the back of this formation.
Concrete has been added to the back of this formation. 02.08.19
02.08.19 - Scaffolding has been removed from this formation now.
Scaffolding has been removed from this formation now. 02.08.19
02.08.19 - Concrete has been applied to th e back of this formation since my last visit.
Concrete has been applied to th e back of this formation since my last visit. 02.08.19
02.08.19 -
02.08.19
02.08.19 -
02.08.19
02.08.19 -
02.08.19
02.08.19 - A crane working on this side of the project too, again no sign of what was being worked on.
A crane working on this side of the project too, again no sign of what was being worked on. 02.08.19
02.08.19 - A team working on the former opening in the building facing Disneyland Drive.
A team working on the former opening in the building facing Disneyland Drive. 02.08.19
02.08.19 - Just a regular door remains where the large access opening was on this side.
Just a regular door remains where the large access opening was on this side. 02.08.19
02.08.19 - The view from the Pixar Pal-A-Round is almost scaffolding free now.
The view from the Pixar Pal-A-Round is almost scaffolding free now. 02.08.19
Back to previous page