01.25.19 - The 3rd floor escalators are now installed and steel for the covers appears to be onsite.
The 3rd floor escalators are now installed and steel for the covers appears to be onsite. 01.25.19
01.25.19 - Scaffolding going up around the 5th floor escalators.
Scaffolding going up around the 5th floor escalators. 01.25.19
01.25.19 - Steel staged on the ground.
Steel staged on the ground. 01.25.19
01.25.19 - More steel.  Guessing this is for the roof structure since it is curved.
More steel. Guessing this is for the roof structure since it is curved. 01.25.19
01.25.19 - 2nd floor escalators
2nd floor escalators 01.25.19
01.25.19 - 3rd floor escalators
3rd floor escalators 01.25.19
01.25.19 - 5th floor escalators
5th floor escalators 01.25.19
01.25.19 - A look at the 6th floor escalators and beyond what appears to be an elevator tower.
A look at the 6th floor escalators and beyond what appears to be an elevator tower. 01.25.19
01.25.19 - A closer look.
A closer look. 01.25.19
01.25.19 - The near structure appears to be a set of elevators too.
The near structure appears to be a set of elevators too. 01.25.19
01.25.19 - The exterior is being added to the structure.
The exterior is being added to the structure. 01.25.19
01.25.19 - Supports for the 6th floor/roof level of the garage are visible.
Supports for the 6th floor/roof level of the garage are visible. 01.25.19
01.25.19 - On the right a crew is erecting a stair case.
On the right a crew is erecting a stair case. 01.25.19
01.25.19 - A closer look at the stair assembly.
A closer look at the stair assembly. 01.25.19
01.25.19 - Work continues on the face of the structure toward the tram stop.
Work continues on the face of the structure toward the tram stop. 01.25.19
01.25.19 - Looks like all the supports and forms are removed from the connection spans for the 6th floor.
Looks like all the supports and forms are removed from the connection spans for the 6th floor. 01.25.19
01.25.19 - This worker was working on the side facing the tram stop.
This worker was working on the side facing the tram stop. 01.25.19
01.25.19 - Looking through the span at the connection spans in the back.
Looking through the span at the connection spans in the back. 01.25.19
01.25.19 - The view from ground level.
The view from ground level. 01.25.19
01.25.19 -
01.25.19
01.25.19 - Walking by on Magic Way.
Walking by on Magic Way. 01.25.19
01.25.19 -
01.25.19
01.25.19 -
01.25.19
01.25.19 -
01.25.19
01.25.19 - Assuming the opening on the 2nd floor is where the new bridge will attach that will span Magic Way.
Assuming the opening on the 2nd floor is where the new bridge will attach that will span Magic Way. 01.25.19
01.25.19 - The view from the Pixar Pal-A-Round.
The view from the Pixar Pal-A-Round. 01.25.19
01.25.19 - Panning to the left you can see forms up on the 5th floor and support columns for the 6th floor in the nearest section.
Panning to the left you can see forms up on the 5th floor and support columns for the 6th floor in the nearest section. 01.25.19
01.25.19 - Panning further to the left crews are working on the center section roof level supports.
Panning further to the left crews are working on the center section roof level supports. 01.25.19
01.25.19 -
01.25.19
01.25.19 - In the back of the structure support columns for the 6th floor are rising up.
In the back of the structure support columns for the 6th floor are rising up. 01.25.19